About Sares Regis Development Investments Property Management Portfolio News
 
   
  Sares-RegisHAYWARD CITY HALL
HAYWARD, CALIFORNIA (pdf version)
 

Symantec Corporation

 

Project

136,000 s.f. turn key City Hall, including one level of subterranean parking

$30 Million

Completed December 1997

SARES REGIS Group of Northern California won the opportunity to structure a unique
public/private partnership with the City of Hayward to develop their new City Hall. This
project from its inception was completed in less than 18 months. SARES REGIS and the
City jointly selected the consultants and contractors. SARES REGIS contracted with the
consultants and contractors to deliver this state-of-the-art project on time and on budget.
The project has a sophisticated seismic design that includes base isolation. Consideration
was also given to green building practices in the use of recycled materials and efficient
mechanical and electrical systems. In addition to the City Hall and its Subterranean
Parking, SARES REGIS completed a 300-Car Parking Structure and a 12,000 s.f. Retail
Space adjacent to the City Hall in 1998.

Development Team

Developer.................................. SARES REGIS Group of Northern California
Shell & Interior Architect.......... Heller•Manus Architects
Landscape Architect................ The Guzzardo Partnership
Contractor.................................. DPR Construction, Inc.

   
 

 